MUNICIPALITY of CENTRE HASTINGS
MUNICIPALITY of CENTRE HASTINGS
PUBLIC WORKS REPORT
April. 2005
COMPLETED
P.W. staff completed removal of winter snow plow
equipment from all trucks and road grader.
Repairs to Truck 8-04 – structural failure of sander
box apron chain housing.
Installation of new bristle segments on John Deere
power sweeper.
Truck 8-10 retro fitted with air line and switch
control to accommodate a water tank and valve for use in dust control
and road grading operations.
P.W. staff completed removal of old railway tie border
from Lawn Bowling Centre.
P.W. crews completed removal of heavy winter sand
build-up on village streets in advance of contracted power sweeper.
Two new streetlights have been installed on the right-of-way
from Whytock St. to swimming pool.
P.W. crews completed installation of water and sewer
services to site of new canteen to be constructed at skate board
park.
ONGOING
Brushing Program – road side clearing of brush for
day lighting of intersections and road signs.
Pothole maintenance on both gravel (grader) and hard
surfaced roads (cold patch). Warm dry weather conditions during
the first half of April have allowed PW crews an opportunity to
apply some maintenance gravel and complete a 2 nd full grading
of a large percentage of these roads. Grader and crews will be
out every day in an ongoing effort to improve and restore road
conditions as road beds continue to dry.
Maintenance and repair of water meters and remote
read-out units on going.
Volvo Loader – PW Supt. continuing to gather information
regarding replacement costs and options for this equipment.
Contracted power vacu-sweeper has begun removal of
winter sand from village streets. This will continue until completion.
FUTURE
Fuller and Clearview Roads – surface treatment (tar
and chip) scheduled for summer 2005.
Preparation of Slab St.E. will commence in May 2005
with surface treatment scheduled for 2006.
Finalize Health and Safety policy documents for adoption
by Council.
Develop program for the replacement an upgrade of
old or damaged road signs. Review current regulations with regards
to addition of new signage if required.
Continue systematic mechanical brushing of rural
roads as prioritized and as budget will allow.
McKenzie St. – install 5 or 6 future water and sewer
services for lots east of Fredrick St.
P.W. crews to construct a walking path along the
right-of-way between Whytock St. and swimming pool as directed
by council.
ISSUES & COMMENTS
Load restrictions for Municipal Roads have been in
effect since Mar. 01/05
Congratulations to Fred Rivers on receiving his Class
1 Water Distribution License.
P.W. Foreman Tom Piszczek attended a prep. course
and wrote his Level II Water Distribution exam. (April 18-22 Belleville).
Unit 8-02 grader broke down for approx. 4 days waiting
for parts. Hired contract grader for road maintenance.
Madoc Twp. resident has requested relief from fees
charged for garbage pick-up in return for allowing Munc. garbage
truck and recycle truck use of his driveway for turnaround. Details
to be provided by Treasurer.
P.W. Supt. and Supv. will attend OGRA road School
at the University of Guelph. 3 day course is for certification
under the Ontario Road Superintendents Program.
P.W. Dept. would like to advise council of the potential
impact that repairs of the significant frost heave damage to Lahey,
Centre, and Old Marmora Rds. will have on the yet to be adopted
2005 Roads Budget.
At the request of Council a general roads tour was
organized and scheduled for early April. All observations and information
gathered will be used in assisting with the updating and implementation
of future Municipal Roads Plans and general maintenance practices. Note: As
discussed and recommended by PW Supt., several rural roads are
in need of an application of crushed gravel to facilitate proper
maintenance during the year. It is suggested a structured 2-3 year
program by developed and implemented to bring identified roads
up to standard. This plan will have to be recognized through the
budgeting process.
Spring season is a very busy time for the Public
Works Dept. Many projects are scheduled and staff try their utmost
to prioritize each project based on urgency, availability of man
power and budgetary constraints. The traveling public in asked
to be cautious and patient when traveling Municipal roadways, especially
during the spring season.
COMRIF Program – It appears The Municipality of Centre
Hastings did not have the submitted projects accepted in the first
draw.
MUNICIPALITY of CENTRE HASTINGS
PUBLIC WORKS REPORT
Mar. 2005
COMPLETED
P.W. staff remained busy responding to several winter
weather events. In order to extent winter sand inventories, PW
Supt. made arrangements to borrow 15 loads of sand from Twp. of
Stirling Rawdon rather than incur high trucking costs due to spring
load restrictions from contractor source.
Repair and service to all snow fighting equipment
after each snow/freezing rain event.
Advertisement and interviews for full time temporary
operator position has now been completed. See comments below.
PW Supt. arranged with representatives from The Municipal
Health and Safety Association to hold a joint meeting with the
Health and Safety Committees from Centre Hastings and Stirling
Rawdon to discuss duties and responsibilities and inspections and
reporting.
P.W. Staff participated in a general health and safety
meeting Mar.24/05.
Municipal Water and Sewer System: - see Water Distribution
Report attached.
ONGOING
Seasonal inspection and clearing of road drainage
and cross culvert blockages due to freeze up.
Brushing Program – road side clearing of brush for
day lighting of intersections and road signs.
Pothole maintenance on both gravel (grader) and hard
surfaced roads (cold patch). Mild temperatures for the last part
of March have thawed the surface of most gravel roads, allowing
PW crews an opportunity to apply gravel and fully grade a large
percentage of these roads. Grader and crews will be out every day
in an ongoing effort to improve and restore road conditions. Note: -
extreme weather variances of wet mild temperatures cycled with
cold freezing temperatures, have contributed to severe degradation
of many Municipal road surfaces, resulting in high maintenance
costs.
Maintenance and repair of water meters and remote
read-out units on going.
Volvo Loader – PW Supt. continuing to gather information
regarding replacement costs and options for this equipment.
FUTURE
Fuller and Clearview Roads – surface treatment (tar
and chip) scheduled for summer 2005.
Preparation of Slab Rd.E. to commence in May 2005
with surface treatment scheduled for 2006.
Development of Salt Management Plan for submission
to OGRA and appropriate Ministries. Draft plan almost completed.
Ministry to be advised of same by PW Supt.
Finalize Health and Safety policy documents for adoption
by Council.
Develop program for the replacement an upgrade of
old or damaged road signs. Review current regulations with regards
to addition of new signage if required.
Continue systematic mechanical brushing of rural
roads as prioritized and as budget will allow.
ISSUES & COMMENTS
PW Supt. has entered into ongoing discussions with
waste management and collection contractors, with a focus on developing
cost savings in this area.
Load restrictions for Municipal Roads have been in
effect since Mar. 01/05
Advertising for a temporary full time operator for
Public Works Dept. closed on Feb. 18/05 with 12 applications received.
All applications were reviewed by administrative staff and short
listed to five applicants. Interviews of the five were scheduled
for Mar.22/05, with four applicants attending and one no-show.
As a result of the interview and selection process, Tony Broek
will be offered the operator position, with a start date of Apr.04/05.
Unit 8-04 – due to a failure in the support structure
of dump box, this unit will need to be taken out of service as
soon as time will allow for repairs. Hopefully this can be done
locally with out sending unit to Kingston.
As mentioned above, the unusual frequency of freezing
rain events this winter season has had a significant impact on
winter control budget.
At the request of Council a general roads tour will
be organized and scheduled for early April. All observations and
information gathered will be used in assisting with the updating
and implementation of future Municipal Roads Plans and general
maintenance practices. Note: As discussed and
recommended by PW Supt., several rural roads are in need of an
application of crushed gravel to facilitate proper maintenance
during the year. It is suggested a structured 2-3 year program
by developed and implemented to bring identified roads up to standard.
This plan will have to be recognized through the budgeting process.
Once again Public Works would like to ask the traveling
public to be cautious and patient when traveling Municipal roadways,
especially during spring season as roads become uneven and rough
due to thawing.
COMRIF Program – Currently nothing new to report.
MUNICIPALITY of CENTRE HASTINGS
PUBLIC WORKS REPORT
Jan. 2005
COMPLETED
- P.W. staff busy responding to several winter weather events,
2 of which involved freezing rain. As a result the initial inventory
of winter sand has been depleted and a full refill of Ivanhoe
dome is underway.
- Repair and service to all snow fighting equipment after each
snow/freezing rain event.
- Russell St. Water Main Repair: - after becoming aware of unusually
high pump hours for the Madoc Village system, PW Staff initiated
an on going leak detection program starting Jan.04/05. This program
included night time isolation and soundings of sections of water
main through out the village. Leak was detected and isolated
on Russell St. at St. Lawrence Jan.10/05 at 11:30 pm. Due to
the high volume of traffic in this area repairs were scheduled
and completed by PW Staff Sunday Jan.16/05.
- Kiwanis Building Emergency Well: - this well pump has now been
repaired and placed back in service for use by the Fire Dept.
as needed. Access to pump will be restricted by lock, keys will
be given to Fire Chief.
- PW Staff completed bi-monthly water meter readings Jan.2005.
- Congratulations to Fred Rivers, Fabian Cooney, Brian Thompson,
and Chris Bateman on official receipt of their Class 1 Water
Distribution Lic.
ONGOING
- Seasonal inspection and clearing of road drainage cross culvert
blockages due to beaver activity and freeze up.
- Brushing Program – road side clearing of brush for day
lighting of intersections and road signs.
- Contractor has begun mechanical brushing of rural roads, starting
on Sills Rd. This will continue as weather permits into Feb.
- Pothole maintenance on both gravel (grader) and hard surfaced
roads (cold patch).
- Maintenance and repair of water meters and remote read-out
units on going
FUTURE
- Fuller and Clearview Roads – surface treatment (tar and
chip) scheduled for summer 2005.
- Preparation of Slab Rd. W. to commence in May 2005 with surface
treatment scheduled for 2006.
- Development of Salt Management Plan for submission to OGRA
and appropriate Ministries.
- Finalize Health and Safety policy documents for adoption by
Council Feb. 2005.
ISSUES & COMMENTS
- Early morning winter patrol – in an effort to
provide a quicker response to early morning slippery road conditions,
P.W. staff have initiated a 5am road patrol program for the winter
season.
- Due to the unusually high number of freezing rain events this
winter season, Public Works has been forced to purchase approx.
double the amount of road salt as compared to last year. Winter
maintenance man hours have also increased significantly.
- Mechanical problems and communication issues led to some complaints
of slow response to some Municipal roads over the Christmas/New
Years holiday period. These issues have been identified and dealt
with and response times greatly improved. Public Works would
ask the public to be patient especially during periods of freezing
rain as it is even more difficult for staff to safely maneuver
large heavy plow/sander units on icy roads.
- P.W. Staff to participate in a general health and safety meeting
Jan.28/05.
- COMRIF Program - P.W. Supt. and Municipal Clerk have been working
with Engineering firm Greer Galloway to prepare Centre Hastings
application for the proposed reconstruction of Spingbrook Rd.
and Moira Rd. including approx. 400m of Ridge Rd. Submission
to the COMRIF Program was made Saturday Jan.08/05.
- Volvo Loader: - With yet another mechanical failure of the
Volvo loader (engine over heating) PW Supt. has made arrangements
with Toromont/Cat to rent a loader for the remainder of to winter
season. Cost estimates for repair to the engine of existing loader
range from $8000. - $24000. not including needed repairs to hydraulic
system and linkage pins and bushings. Staff will be gathering
information and costs for recommendation to council at future
meeting.
- Pump Rates: - After repairs to Russell St. water main, pump
cycle times were significantly reduced but still above normal.
Under the supervision of PW Supv. staff is continuing the search
for other leakage with assistance from Canadian Leak Detection
(Jan.21/05).
PUBLIC WORKS REPORT - Oct.
2004
COMPLETED
1.
Springbrook Rd., Moira Rd., and Crookston Rd. gravel shoulder maintenance
(grading) completed in preparation for winter season.
2.
Fuller Rd. Reconstruction project. – completed ditching,
excavation cuts on hills to improve site lines, driving surface
rock removal, installation of new and replacement of damaged culverts,
and spreading of 3” minus crushed limestone material on grade
raise areas. Note: Municipal P.W. staff and equipment used extensively
on this project to control costs.
3.
Centre Road – repairs to sink hole in center of road as a
result of cross culvert failure.
4.
P.W. crews installed several entrance culverts during the month.
5.
Winter Sand – the Ivanhoe dome has been filled with approx.
3600 t of winter sand mix.
6.
Training - Public Works Supt. and Foreman attended a 2 day Snow
and Ice seminar sponsored by OGRA. Hot Topics – development
of Salt Management Plans, increased usage of pre-wet and anti-icing
technologies by large and small Municipalities, and large display
of new snow and ice fighting equipment and technologies. Oct 21 & 22
/04
7.
Training - Public Works Supt. and Supv. along with Fred Rivers
and Fabian Cooney attended the fall EOWWA (Eastern Ontario Water
and Wastewater Assoc.) Conference in Ottawa. Oct. 20/04
8.
Installation of a new 6” isolation valve on the Russell St.
Water line.
9.
Disability Access Program – curb cutting and sidewalk sloping
at corners on St.Peters, Rollins, Prince Albert, and Madawaska
Sts. (8 corners) has now been completed.
10.
Repaired residential sewer blockage at 159 St. Lawrence St. Replaced
14’ of sanitary pipe.
11.
Water testing – organic and inorganic testing completed on
water supplies for Madoc Arena and Moira Hall.
ONGOING
1.
Guard Rail Post – removal and replacement of old or damaged
posts will be ongoing thought the fall season.
2.
Seasonal inspection and clearing of road drainage cross culvert
blockages due to beaver activity.
3.
Brushing Program – road side clearing of brush for day lighting
of intersections and road signs.
4.
Pothole maintenance on both gravel (grader) and hard surfaced roads
(cold patch).
5.
Fuller Rd. and Clearview Rd. – upgrade and prepare for surface
treatment in 2005, started in May. Clearview Rd. to be prepared in conjunction with
City of Belleville – now COMPLETED. - Fuller
Rd. brushing to be completed in Aug. with excavation work to
commence Aug. 30th. The intent would be to use P.W.
staff and equipment as much as possible to help control construction
costs. This effort may delay some lower priority projects. See
item #2 above for update.
6.
Flushing of selected hydrants in the Urban Centre will continue
through Nov.
7.
Maintenance and repair of water meters and remote read-out units
on going.
8.
Construction of the Market Square Project nearing the fall completion
date.
9.
P.W. Staff assisting when needed with the development of new Skate
Board Park.
FUTURE
1.
Bridge and culvert inspections have begun by Engineering Consultants
Greer Galloway of Belleville. Reports expected by mid Nov.
2.
Completion of Fuller road reconstruction project with application,
grading, and compaction of Gran “A” material by mid
Nov.
3.
Urban Paving – Hot mix pavement repairs in Urban Centre to
start 1st week in Nov. Completion will take about 1
week.
4.
Service program for all equipment and plow trucks in the 1st half
of Nov. in preparation for the on set of winter.
5.
Seek estimates to re-commission well and controls at Kiwanis Centre
Fire Hydrant on St.Lawrence St. E. (Fire Dept. use only)
ISSUES & COMMENTS
1.
Volvo Loader – once again our aging loader has developed
cooling system problems. Every effort will be made to reduce unnecessary
use of this machine in order to assure availability for loading
of winter sand over winter season.
2.
Sill’s Road Truck Traffic Issue – at the request of
Council and the Transportation Committee, P.W. Staff have continued
to monitor truck traffic and pit activity on Sill’s road
as related to the gravel pits on this road. The only activity noted
has been the very recent loading and hauling of the crushed gravel
material from one of these locations. This activity has been light
and sporadic. The Ministry of Natural Resources office in Peterborough
was contacted and it was confirmed that all pits were licensed
under the Pits and Quarries Act and that there were no Lic. Conditions
that restricted hours of operation or days of operation. Based
on the forgoing observations and information and the fact that
there has not been any further complaints to the Public Works Dept.
regarding this issue, there appears to be no reason to establish
a reduced speed zone or truck traffic restrictions for the eastern
portion of Sill’s road.
3.
Ambulance/Fire hall – P.W. Supt. was able negotiate a shared
cost solution to correct the water leakage problem at this facility.
Under the agreement the original General Contractor will supply
all the labour required to install metal siding on the upper portion
of the west block wall, and the Municipality will pay for the materials.
This project to be completed by mid Nov.
4.
Public Library – in order to correct water seepage and back
up problems at the Madoc Library, P.W. Staff replaced the existing
sump pump that appeared to be intermittent and again negotiated
a shared cost plan with the original General Contractor to correct
the outside perimeter drainage and control of rain water run off.
This project to be completed by mid Nov.
|