St Lawrence & Durham Construction Weekly Schedule Update - Sept 22nd to Sept 26th,2025

Weekly Construction Update
Dates: Monday – Friday
Location: Village of Madoc
General Work
-
Sidewalk / Curb Prep: Ongoing additional preparation throughout town.
-
Deficiency Work: Corrections and deficiency repairs on St. Lawrence Street and Durham Street.
Curbside Work
-
Tuesday:
-
Concrete curb and sidewalk pours will commence at various locations across town.
-
Important Notes
-
Surface Asphalt Paving:
-
GIP Paving is scheduled to begin surface asphalt paving on Durham Street and St. Lawrence Street starting Monday, September 30 (weather permitting).
-
-
Resident & Business Notices:
-
CDS will begin delivering notices to affected businesses and residents starting Monday.
-