St Lawrence Street and Durham Street Reconstruction Weekly Update: JUNE 23 TO JUNE 27, 2025

Here is the weekly update regarding the St Lawrence Street & Durham Street Reconstruction for the week of June 23 to June 27, 2025.
St. Lawrence Street East
-
Phase 3B – Work progressing easterly; momentum slightly slower due to rock conditions.
-
Phase 3A – Continuing easterly progression.
-
Davidson to Wellington – Topsoil placement and sodding underway.
Durham Street North
-
Rock excavation services ongoing.
-
Possible mobilization of a second hoe-ram to assist with excavation efforts.